About

Project Timeline

Notes icon

2013

Dominion Energy executed lease agreement with Bureau of Ocean Energy Management (BOEM)
Plan icon

2016

Dominion Energy submitted Site Assessment Plan to BOEM
Notes icon

2017

BOEM approved Site Assessment Plan
Project icon

2019

Dominion Energy announced committment to CVOW
Check icon

2020

Virginia General Assembly passed supportive legislation
Dominion Energy submitted Construction and Operations Plan (COP) to BOEM
Paper in hand icon

2021

Dominion Energy executed major contracts
Dominion Energy filed for Virginia State Corporation Commission (SCC) review
Check icon

2022

CVOW approved by SCC
Check icon

September 2023

Final Environmental Impact Statement Issued

October 2023

First Monopiles Delivered to Hampton Roads

The first eight monopile foundations were delivered to Portsmouth Marine Terminal (PMT). They continue to arrive at PMT for staging prior to installation in the lease area.

Notes icon

October 2023

BOEM Record of Decision

November 2023

Transmission construction started
Transmission construction

Onshore construction for the underground onshore export circuits started. This integral work will allow the energy generated from the wind turbines offshore to be connected to the grid onshore.

April 2024

Substation Pin Piles arrived in Hampton Roads
Pin Pile construction

Twelve pin piles were loaded at Portsmouth Marine Terminal. They will serve as the foundation for the three offshore substations supporting the project.

May 2024

First Monopiles Loaded for Installation
Monopiles being loaded for installation

The first six monopiles were loaded onto the Orion installation vessel at Portsmouth Marine Terminal.

First Monopile Installed
Monopiles being installed

The first six monopiles were installed in the Northwest corner of the project lease area. The monopile installation will occur from May 1 through October 31 to avoid the North Atlantic right whale migration season and is anticipated to continue through 2025.

October 2024

First Pin Piles Installed
Pinpiles being installed

The Orion installed the first round of pin piles, placing four into the ocean floor. These pin piles support the roughly 4,000-ton offshore substation.

Export Cable Laying Began
Export cable laying

DEME Group and Prysmian began laying 365 miles of cable 8 feet below the ocean floor.

First Monopile Installation Season Concluded
Marine lighting on foundations

During the five-month installation season, Dominion Energy placed 78 monopile foundations and four offshore substation foundations.

December 2024

More Components Arrive in Hampton Roads
Components arrive in Hampton Roads

Various offshore components were delivered to Portsmouth Marine Terminal (PMT) throughout 2024, totaling 110 monopiles, 51 transition pieces, and 12 pin piles.

January 2025

First Transition Piece Installed
First transition piece installed offshore

A transition piece is the yellow reinforcing structure that connects the monopile foundation below the water to the wind turbine tower above the water. These pieces contain platforms and ladders that allow our wind turbine technicians to easily access the turbine for routine maintenance.

March 2025

First Offshore Substation Installed
First Offshore Substation #3 installed

After making a trip across the Atlantic Ocean from Denmark, the first offshore substation was installed off the coast of Virginia Beach. Energy generated by the wind turbines is bundled at the offshore substation, stepped up to 230kV and then exported to shore.

2025-2026

Project construction and commissioning
Building the windmill