About

Project Timeline

Notes icon

2013

Dominion Energy executed lease agreement with Bureau of Ocean Energy Management (BOEM)
Plan icon

2016

Dominion Energy submitted Site Assessment Plan to BOEM
Notes icon

2017

BOEM approved Site Assessment Plan
Project icon

2019

Dominion Energy announces committment to CVOW
Check icon

2020

Virginia General Assembly passed supportive legislation
Dominion Energy submitted Construction and Operations Plan (COP) to BOEM
Paper in hand icon

2021

Dominion Energy executed major contracts
Dominion Energy filed for Virginia State Corporation Commission (SCC) review
Check icon

2022

CVOW approved by SCC
Check icon

September 2023

Final Environmental Impact Statement Issued

October 2023

First Monopiles Delivered to Hampton Roads

The first eight monopile foundations were delivered to Portsmouth Marine Terminal (PMT). They continue to arrive at PMT for staging prior to installation in the lease area.

Notes icon

October 2023

BOEM Record of Decision

November 2023

Transmission construction started
Transmission construction

Onshore construction for the underground onshore export circuits started. This integral work will allow the energy generated from the wind turbines offshore to be connected to the grid onshore.

April 2024

Substation Pin Piles arrived in Hampton Roads
Pin Pile construction

Twelve pin piles were loaded at Portsmouth Marine Terminal. They will serve as the foundation for the three offshore substations supporting the project.

May 2024

First Monopiles Loaded for Installation
Monopiles being loaded for installation

The first six monopiles were loaded onto the Orion installation vessel at Portsmouth Marine Terminal.

First Monopile Installed
Monopiles being installed

The first six monopiles were installed in the Northwest corner of the project lease area. The monopile installation will occur from May 1 through October 31 to avoid the North Atlantic right whale migration season and is anticipated to continue through 2025.

2024-2026

Project construction and commissioning
Building the windmill